Last Planner benefits

Last Planner® benefits

In the UK we have worked on:

  • two Waitrose projects where it created a 20% programme reduction for two different constructors;

  • a school project delivered 12 weeks early when the project was running 4 weeks late with 48 to go;

  • a city-centre housing project delivered 2 weeks early after it was 7 weeks late with half of the 70 week construction period left to run;

  • a Travel Inn & restaurant delivered in 14 weeks instead of 20. 

These are some of the more spectacular results.  It’s used on civil engineering, hotel, health & commercial projects too.  Few of these projects used 100% of Last Planner.

In South Africa we are working with a civils team working through the uncertainty of the rainy season on enabling works for an open-cast pit.

Last Planner offers a wide range of benefits – many are summarised in